Project Background
Different Dog is an innovative pet food company based in Telford, focused on delivering freshly cooked, all natural pet food. With rapid growth from a small startup to a robust team of 90 professionals, they needed a state-of-the-art facility to support their expanding operations. Ambrey Baker Construction was tasked with transforming their existing space into a modern kitchen and production hub.

Scope of Work
Drainage System: Designed and installed a highc apacity drainage system, integrating durable piping through reinforced concrete, and conducted CCTV inspections for quality assurance. A new manhole was added to facilitate maintenance.

Cold Storage: Constructed cold storage units with custom-built insulated panels, food-safe silicone seals, and hygienic cladding, ensuring the safestorage of ingredients and products.

Temporary Facility: Developed a temporary facility with designated hand-wash areas, wash zones, and ingredient preparation rooms to maintain production during renovations.

Logistics Enhancements: Installed doors, ramps, and PVC curtains for better hygiene and operational efficiency.

Future-Proofing: Laid the groundwork for Phase Two, which will include expanding the mezzanine floor for office spaces and reconfiguring existing areas for increased functionality.

“Our work with Different Dog has been a remarkable example of how thoughtful design and tailored solutions can make a significant impact on operational efficiency and growth. We’re proud to be part of their journey, ensuring that each phase of development is built on quality, compliance, and innovation to support their ambitious goals.”

Carl Duffy - Commercial Director

Challenge: Insuring the drainage system could handle high production volumes.
Solution: Conducted thorough inspections and customized the piping and drainage layout for optimal capacity and durability.

Challenge: Aligning construction timelines with operational demands.
Solution: Phased the project strategically, completing Phase One to support immediate needs and planning Phase Two for future enhancements.

Challenge: Exceding requirements of food-grade construction standards.
Solution: Collaborated closely with Different Dog’s team and sourced specialised materials like food safe cladding and silicone seals, ensuring compliance with industry regulations.

Related Case Studies

Melton Foods – Elevating Amenities
13 December 2023

At Ambrey Baker, we take pride in contributing to the success of esteemed clients, and our recent collaboration with Melton Foods on a comprehensive facilities...

Research and Development Kitchen for Food Manufacturer
17 September 2024

Project Background A leading food manufacturer known for their innovation and quality, embarked on a project to create a state-of-the-art research and development facility to...

RAAC Remediation & Ceiling Replacement for Food Manufacturer
4 October 2024

Project Background A leading global food manufacturer, significant issues at a key UK factory, involving the presence of HSE condemned materials; A Reinforced Autoclaved Aerated...

Skip to content